Owner-Controlled Digital Execution Environment

Overview

Vista’s System Integration team served as a bridge between the owner’s project team, their corporate IT department, and the project’s third-party engineering contractors to implement the software, work processes, and educate all the project participants.

Client

A major oil and gas owner-operator requiring a datacentric infrastructure to be established for an expansion of an existing asset.

Project facility

Downstream facility expansion.

Situation

After completing the conceptual and design basis memorandum (DBM) work for a downstream facility expansion using a conventional engineering approach and tools, the client wanted to investigate other means of project execution before starting the next phase of the project.

The primary concerns included visibility of EPC change orders and the inability to access information needed to support the project and operations. The client had experienced similar issues in executing other projects where information sharing was not seamless across the owner-EPC interface.

Solution

The client needed a tool that enabled them to control project information and share it with all project participants. The solution was to implement an owner-controlled digital project hub before the start of front-end engineering design (FEED).

The hub included an integrated suite of engineering and design applications along with a data portal to facilitate the sharing of data among various applications. All contractors were required to perform their work within the owner’s hub.

Vista’s team served as a bridge between the owner’s project team, their corporate IT department, and the project-engineering contractors to implement the software, work processes, and educate all the project participants.

Because the early phase project deliverables were completed under the conventional execution model, this information needed to be converted and input into the hub. The conversion and data population activities were conducted in parallel to other DBM phase activities to avoid delaying the start of FEED.

The data conversion process revealed errors in the engineering deliverables, which is typical of the conventional engineering approach. These errors were corrected during the conversion process to establish a reliable and accurate set of project data before going into FEED. The deliverables included the following errors:

  • Incorrect or missing document references. For example, off-page connectors (OPCs), which show a connection between two assets on two separate piping and instrumentation diagrams (P&IDs), were either missing or pointing to the wrong connection point.
  • Mismatched lists (i.e., 1D deliverables) and drawings (i.e., 2D deliverables)
  • Discrepancies in information across disciplines. For example, information on P&IDs and the instrument index did not agree.

Outcomes

The observed outcomes included:

  • Significantly enhanced data integrity
  • Avoidance of costly data errors
  • Reduced lead time on many scheduled activities
  • Simplified interfaces among the project participants
  • Real-time access to information

Fixing information errors before FEED is critical to avoid time-consuming and expensive actions during FEED to fix these issues. Using the data portal hub and establishing high-integrity, baseline data with allowed the client to maintain consistent data throughout the subsequent project phases and easily retrieve information to manage the project effectively.

As FEED progressed, the project team worked through issues concerning changing from a conventional engineering approach to a digital one. Like most EPCs, the engineering contractor had many work practices and quality procedures based on a document-centric approach. Vista helped the team address these issues systematically before work started on a task.

Another benefit of the data-centric approach realized during FEED was a two-thirds reduction in the time required to create a cost estimate based on material take-offs. The time saving was achieved by eliminating the task of manually extracting information from documents and inputting it into the cost model.

During the project, multiple engineering contractors were able to works concurrently and seamlessly within a single environment, eliminating the many interface issues that typically arise among the project participants.

The owner team had real-time access to project information allowing a more proactive collaboration between the client and its engineering contractors – logistical meetings around the timing of information delivery were mostly eliminated.

Lessons Learned

The cost of data conversion was a relatively small cost compared with the savings realized by the information accessibilty via the technical data portal. This case study illustrates the advantages of implementing a data-centric approach to digital execution architecture at the outset of engineering.

Need help integrating your systems? Start your digital transformation today.

Data-centric Execution

Datacentric PDF DL